board of ingham county
road commissioners
supersedes
BP#223 resolution #079-06
subject: Bidding Procedures
Ingham
County Road Commission invitations for bids and proposals for maintenance and
construction projects, materials (except as provided by Board Policy #220 -
“Setting Bid Dates for Routine Items”) and equipment shall be set by the Board
for bid opening by staff and the bids shall be received and opened at the time
and date set, subject to the following:
1. Any bids that may be received after the date
and time set for the bid opening shall be rejected and
returned, unopened, to the bidder.
2. When required, cashier’s
checks, certified checks or money orders will be accepted as bid guarantees on
construction and maintenance projects.
3. Any bid or proposal for which a bid security
is required in a specified amount, which fails to have the bid security
attached as required, shall be rejected
and returned to the bidder.
4. Other than as set forth above, the
determination of acceptance or rejection of bids and the waiver of
irregularities shall be made by the Board of Ingham County Road Commissioners
at a regular or special meeting.
5. The Board of Ingham County Road
Commissioners reserves the right to reject any or all proposals or to waive
defects and to accept the proposal in part or entirety that, in the judgment of
the Board, is in the best interest and to the advantage of the Board of Ingham
County Road Commissioners and the County of Ingham, Michigan.
6. In the event that an outside contractor or
consultant is used to develop bid specifications, such specifications shall be
written in as generic language as possible while still adequately describing
the products or services to be obtained.
The contractor or consultant developing or assisting in the development
of the bid specifications is precluded from bidding on those specifications, or
assisting any other bidder with respect to bidding, on those bid
specifications. Any such bid that is
received shall be returned unopened. If
opened, that bid shall not be accepted.
7. Each request for proposal developed, all or
in part, by an outside contractor/consultant shall stipulate that each bidder
shall submit a statement that it has no contractual agreements with, and/or has
neither given nor received any remuneration within the prior twelve (12) months
to or from, the consultant/contractor developing the bid specifications.
8. Violation of this policy will be considered
a violation of the contract, and vice versa.
9. Inclusion of paragraphs 6 and 7 herein by
reference is hereby required in any such bidding and/or contract documents.
10. This policy shall become effective immediately and supersedes Board Policy #198 dated 09/30/93 and Board Policy #223 dated 06/24/96.